Westgate Connector £6m cycle route works begin in Leeds
Round-the-clock lane closures start on Burley Street, Park Lane and Westgate as Bethell builds a segregated cycle route due to finish in summer 2027.

Leeds City Council has started construction on the Westgate Connector, a scheme to add a two-way segregated cycle lane, safer crossings and redesigned junctions along Burley Street, Park Lane and Westgate on the western edge of the city centre.
The scheme is funded by £6 million from Active Travel England and delivered with the West Yorkshire Combined Authority, and work began on Monday 9 November and is due to run until summer 2027.
Safety record on the Westgate Connector route
The route carries more than 4,200 people walking, wheeling and cycling along Burley Street every day, many of them students. The council says crossing the road at Westgate Gyratory and Hanover Way can feel unsafe because of the complex road layout. Between 2021 and 2025 there were 39 reported casualties along the route, seven of them serious.
Once finished, the scheme will extend the cycle network to the west of the city centre, improve pedestrian crossings and upgrade and relocate bus stops. The council links it to its Vision Zero aim of eliminating road deaths and serious injuries in Leeds by 2040.
Councillor Tom Hinchcliffe, Leeds City Council’s executive member for transport and planning, said: “The Burley Road to Westgate project is a step towards our vision for a safer, greener, and more connected Leeds. By providing dedicated cycling and walking spaces, we can prioritise safety and support the city’s goals for health, sustainability, and reducing carbon emissions.”
“The project will also support local employment and apprenticeship opportunities across the Leeds city region.”
Michael Holmes, Managing Director, Bethell
Lane closures and diversions on Park Lane
Lane closures are in place around the clock from this week, with signed diversions and temporary bus stops where needed. The council says routes will be kept open wherever possible and some work will be done overnight to limit disruption. For the first four weeks, crews will work mainly from 7.30am to 5pm on weekdays. They will prepare new traffic signals at the Park Lane and Hanover Way junction and an improved crossing near Rutland Mount, divert utilities on Park Lane for new bus shelters and extend cycle facilities at Westgate Point.
The contract went to Bethell, a civil engineering firm headquartered in Kearsley, Greater Manchester, with a regional office in Morley. Michael Holmes, managing director at Bethell, said: “We will carefully phase the work to minimise disruption while creating safer and better-connected routes for people walking, wheeling and cycling.”
The Westgate Connector is one of several highway projects changing the edges of the city centre, alongside the £120m ring road programme and the newly finished Leeds Station Gateway. The council will contact residents and businesses directly affected by the works.
Sources: Leeds City Council news release, 9 November 2026; West Yorkshire Combined Authority, Westgate Connector business case summary